(a)
|
Effective Date. |
|
|
(1)
|
No later than 120 days after the approval of this section by the Office
of Administrative Law, each air pollution control and air quality management district must: |
|
|
|
(A)
|
Implement and enforce the requirements of this section; or |
|
|
|
(B)
|
Propose their own asbestos airborne toxic control measure as provided in Health and Safety
Code section 39666(d). |
|
|
(2)
|
Pre-Existing Operations: The owner / operator of any project in which the construction, grading, quarrying,
or surface mining operation started before the effective date of this section shall comply with this
section by: |
|
|
|
(A)
|
The date the district begins implementing and enforcing this section as required in subsection (a)(1)(A); |
|
|
|
(B)
|
The compliance date specified in the airborne toxic control measure adopted by the district
as required in subsection (a)(1)(B). |
|
(b)
|
Applicability. Unless
one of the specific exemptions specified in subsection (c) applies, this section shall apply to any construction,
grading, quarrying, or surface mining operation on any property that meets any of the following criteria: |
|
|
(1)
|
Any portion of the area to be disturbed is located in a geographic ultramafic
rock unit; or |
|
|
(2)
|
Any portion of the area to be disturbed has naturally-occurring asbestos,
serpentine, or ultramafic rock as determined by the owner / operator, or the Air Pollution Control Officer (APCO);
or |
|
|
(3)
|
Naturally-occurring asbestos, serpentine, or ultramafic rock is discovered
by the owner / operator, a registered geologist, or the APCO in the area to be disturbed after the start of any construction,
grading, quarrying, or surface mining operation. |
|
(c)
|
General Exemptions. |
|
|
(1)
|
Geologic Evaluation: The APCO may provide an exemption from this section for any property that meets
the criterion in subsection (b)(1) if a registered geologist has conducted a geologic evaluation of the property
and determined that no serpentine or ultramafic rock is likely to be found in the area to be disturbed. Before
an exemption can be granted, the owner/operator must provide a copy of a report detailing the geologic evaluation
to the APCO for his or her consideration. |
|
|
|
(A)
|
At a minimum, the geologic evaluation must include:
|
1.
|
A general description of the property and the proposed use; |
|
2.
|
A detailed site characterization which may include: |
| |
i.
|
A physical site inspection; |
| |
ii.
|
Offsite geologic evaluation of adjacent property; |
| |
iii.
|
Evaluation of existing geological maps and studies of the site and surrounding area; |
| |
iv.
|
Development of geologic maps of the site and vicinity; |
| |
v.
|
Identification and description of geologic units, rock and soil types, and
features that could be related to the presence of ultramafic rocks, serpentine, or asbestos mineralization;
and |
| |
vi.
|
A subsurface investigation to evaluate the nature and extent of geologic
materials in the subsurface where vertical excavation is planned; methods of subsurface investigation may
include, but are not limited to borings, test pits, trenching, and geophysical surveys; |
|
3.
|
A classification of rock types found must conform to the nomenclature based
on the International Union of Geological Science system; |
|
4.
|
A description of the sampling procedures used; |
|
5.
|
A description of the analytical procedures used, which may include mineralogical
analyses, petrographic analyses, chemical analyses, or analyses for asbestos content; |
|
6.
|
An archive of collected rock samples for third party examination; and |
|
7.
|
A geologic evaluation report documenting observations, methods, data, and
findings; the format and content of the report should follow the Guidelines for Engineering Geologic Reports
issued by the State Board of Registration for Geologists and Geophysicists. |
|
|
|
|
(B)
|
The district may request any additional tests or other information needed
to evaluate an application for exemption. |
|
|
|
(C)
|
The district shall grant or deny a request for an exemption within 90 days
of the receipt of a complete application. |
|
|
|
(D)
|
If the request for an exemption is denied, the APCO shall provide written
reasons for the denial. |
|
|
|
(E)
|
Expiration of the Geologic Exemption: If the owner / operator discovers any naturally-occurring asbestos, serpentine, or ultramafic
rock in the area to be disturbed after the exemption is granted, then:
|
1.
|
The owner / operator must comply with the requirements of this section; |
|
2.
|
The owner / operator must report the discovery of the naturally-occurring
asbestos, serpentine, or ultramafic rock to the APCO no later than the next business day; and |
|
3.
|
The exemption under subsection (c)(1) shall expire and cease to be effective. |
|
|
|
(2)
|
If a method is developed to accurately demonstrate that property located
in a geographic ultramafic rock unit has no detectable asbestos in the area to be disturbed, then the ARB
Executive Officer shall propose to the Board for adoption a regulatory amendment allowing the method
to be utilized, as appropriate, to obtain an exemption from the requirements specified in this section. |
|
|
(3)
|
Agriculture and Timber Harvesting: This section shall not apply to agricultural
operations or timber harvesting except for construction of roads and buildings. Construction of roads is subject
to the requirements of subsection (e) if the road is part of a construction or grading operation, quarry,
or surface mine, and is subject to the requirements of subsection (d) if the road is not part of
a construction or grading operation, quarry, or surface mine. |
|
|
(4)
|
Homeowners and Tenants: Individuals engaged in covered activities on residential property they own
or occupy are exempt from subsections (e)(1) and (e)(3)(A). |
|
|
(5)
|
Sand and Gravel Operations: The APCO may provide an exemption for crushing, screening and conveying equipment,
stockpiles, and off-site material transport at a sand and gravel operation if the operation processes only materials
from an alluvial deposit. |
|
|
|
(A)
|
The district shall grant or deny a request for an exemption within ninety (90) days
of the receipt of a complete application. |
|
|
|
(B)
|
If the request for an exemption is denied, the APCO shall provide written
reasons for the denial. |
|
(d)
|
Requirements for Road Construction and Maintenance. These requirements shall apply to roads that are not part of a construction
or grading project, quarry, or surface mine. |
|
|
(1)
|
No person shall conduct any road construction or maintenance activities
that disturb any area that meets any criterion listed in subsections (b)(1) or (b)(2) unless all
of the following conditions are met. |
|
|
|
(A)
|
The APCO is notified in writing at least fourteen (14) days before the beginning of the activity
or in accordance with a procedure approved by the district. |
|
|
|
(B)
|
All the following dust control measures are implemented during any road
construction or maintenance activity:
|
1.
|
Unpaved areas subject to vehicle traffic must be stabilized by being kept adequately
wetted, treated with a chemical dust suppressant, or covered with material that contains less than 0.25 percent
asbestos; |
|
2.
|
The speed of any vehicles and equipment traveling across unpaved areas must
be no more than fifteen (15) miles per hour unless the road surface and surrounding area is sufficiently stabilized
to prevent vehicles and equipment traveling more than 15 miles per hour from emitting dust that is visible
crossing the project boundaries; |
|
3.
|
Storage piles and disturbed areas not subject to vehicular traffic must be stabilized
by being kept adequately wetted, treated with a chemical dust suppressant, or covered with material that contains less than
0.25 percent asbestos; and |
|
4.
|
Activities must be conducted so that no track-out from any road construction
project is visible on any paved roadway open to the public. |
|
|
|
|
(C)
|
Equipment and operations must not cause the emission of any dust that is
visible crossing the project boundaries. |
|
|
(2)
|
No person shall conduct any road construction or maintenance activity that
disturbs the ground surface in an area that meets the criteria in subsection (b)(3) unless: |
|
|
|
(A)
|
The APCO is notified no later than the next business day of the discovery
that the area meets the criteria in subsection (b)(3); and |
|
|
|
(B)
|
The requirements of subsections (d)(1)(B) through (d)(1)(C), are implemented
within twenty-four (24) hours of the discovery. |
|
|
(3)
|
Exemptions from the Requirements for Road Construction and Maintenance. The following exemptions may apply in addition to the applicable general exemptions
specified in subsection (c). |
|
|
|
(A)
|
Emergency Road Repairs:
Subsection (d)(1)(A) shall not apply when construction of a road or firebreak, or a road repair is necessary
due to a landslide, flood, or other emergency or to mitigate a condition that constitutes an imminent
hazard to the public. The owner / operator shall notify the APCO no later than the next business day
of the action taken and the condition establishing the applicability of this subsection. |
|
|
|
(B)
|
Remote Locations:
The APCO may provide an exemption from the requirements of subsection (d) for any activity which
will occur at a remote location.
|
1.
|
The district shall grant or deny a request for an exemption within ninety (90) days
of the receipt of a complete application. |
|
2.
|
If the request for an exemption is denied, the APCO shall provide written reasons
for the denial. |
|
|
(e)
|
Requirements for Construction and Grading Operations. |
|
|
(1)
|
Areas of One Acre or Less Meeting the Criteria in Subsections (b)(1)
or (b)(2): No
person shall engage in any construction or grading operation on property where the area to be
disturbed is one (1.0) acre or less unless all of the following dust mitigation measures are initiated at the start and
maintained throughout the duration of the construction or grading activity: |
|
|
|
(A)
|
Construction vehicle speed at the work site must be limited to fifteen (15) miles
per hour or less; |
|
|
|
(B)
|
Prior to any ground disturbance, sufficient water must be applied to the
area to be disturbed to prevent visible emissions from crossing the property line; |
|
|
|
(C)
|
Areas to be graded or excavated must be kept adequately wetted to prevent
visible emissions from crossing the property line; |
|
|
|
(D)
|
Storage piles must be kept adequately wetted, treated with a chemical dust
suppressant, or covered when material is not being added to or removed from the pile; |
|
|
|
(E)
|
Equipment must be washed down before moving from the property onto a paved public road;
and |
|
|
|
(F)
|
Visible track-out on the paved public road must be cleaned using wet sweeping or a HEPA
filter equipped vacuum device within twenty-four (24) hours. |
|
|
(2)
|
Areas Greater Than One Acre Meeting the Criteria in Subsections (b)(1)
or (b)(2):
No person shall engage in any construction or grading operation on property where the area to be disturbed
is greater than one (1.0) acre unless: |
|
|
|
(A)
|
An Asbestos Dust Mitigation Plan for the operation has been:
|
1.
|
Submitted to and approved by the district before the start of any construction
or grading activity; and |
|
2.
|
The provisions of that dust mitigation plan are implemented at the beginning
and maintained throughout the duration of the construction or grading activity; and |
|
|
|
|
(B)
|
For a project started before the effective date of this section for which
an asbestos dust mitigation plan was submitted at least sixty (60) days before the effective date, and for
which the district has not yet approved the asbestos dust mitigation plan:
|
1.
|
The measures in subsection (e)(1) must be implemented and maintained until
the district-approved asbestos dust mitigation plan is implemented; and |
|
2.
|
The provisions of the district-approved asbestos dust mitigation plan must be
implemented within fourteen (14) days of district approval of the plan and maintained throughout the
remainder of the construction or grading activity. |
|
|
|
(3)
|
Property That Meets the Criteria in Subsection (b)(3): No person shall engage in
any construction or grading operation unless the following requirements are met: |
|
|
|
(A)
|
The owner / operator notifies the district of the discovery of naturally-occurring
asbestos, serpentine, or ultramafic rock no later than the next business day; |
|
|
|
(B)
|
The dust mitigation measures in subsection (e)(1) are implemented within
twenty-four (24) hours after determining that the property meets the criteria in subsection (b)(3);
and |
|
|
|
(C)
|
For operations in which the area to be disturbed is one (1.0) acre or less, the dust mitigation
measures in subsection (e)(1) are maintained throughout the duration of the construction or grading activity;
or |
|
|
|
(D)
|
For operations in which the area to be disturbed is greater than one (1.0) acre, the owner
/ operator must:
|
1.
|
Submit an asbestos dust mitigation plan to the district within fourteen (14) days
of the discovery of naturally-occurring asbestos, serpentine, or ultramafic rock; |
|
2.
|
Maintain the dust mitigation measures in subsection (e)(1) until the provisions
of the district-approved asbestos dust mitigation plan are implemented; |
|
3.
|
Implement the provisions of the district-approved asbestos dust mitigation plan within
fourteen (14) days of district approval of the plan; and |
|
4.
|
Maintain the provisions of the district-approved asbestos dust mitigation plan
throughout the remainder of the construction or grading activity. |
|
|
|
(4)
|
Asbestos Dust Mitigation Plans: An Asbestos Dust Mitigation Plan must specify dust mitigation practices which
are sufficient to ensure that no equipment or operation emits dust that is visible crossing the property line,
and must include one or more provisions addressing each of the following topics. |
|
|
|
(A)
|
Track-out prevention and control measures which shall include:
|
1.
|
Removal of any visible track-out from a paved public road at any location
where vehicles exit the work site; this shall be accomplished using wet sweeping or a HEPA filter equipped
vacuum device at the end of the work day or at least one time per day; and |
|
2.
|
Installation of one or more of the following track-out prevention measures: |
|
|
i.
|
A gravel pad designed using good engineering practices to clean the tires of exiting
vehicles; |
|
|
ii.
|
A tire shaker; |
|
|
iii.
|
A wheel wash system; |
|
|
iv.
|
Pavement extending for not less than fifty (50) consecutive feet from the intersection
with the paved public road; or |
|
|
v.
|
Any other measure as effective as the measures listed above. |
|
|
|
|
(B)
|
Keeping active storage piles adequately wetted or covered with tarps. |
|
|
|
(C)
|
Control for disturbed surface areas and storage piles that will remain inactive
for more than seven (7) days, which shall include one or more of the following:
|
1.
|
Keep the surface adequately wetted; |
|
2.
|
Establishment and maintenance of surface crusting sufficient to satisfy the
test in subsection (h)(6); |
|
3.
|
Application of chemical dust suppressants or chemical stabilizers according
to the manufacturers' recommendations; |
|
4.
|
Covering with tarp(s) or vegetative cover; |
|
5.
|
Installation of wind barriers of fifty (50) percent porosity around three (3) sides
of a storage pile; |
|
6.
|
Installation of wind barriers across open areas; or |
|
7.
|
Any other measure as effective as the measures listed above. |
|
|
|
|
(D)
|
Control for traffic on on-site unpaved roads, parking lots, and staging
areas which shall include:
|
1.
|
A maximum vehicle speed limit of fifteen (15) miles per hour or less; and |
|
2.
|
One or more of the following: |
|
|
i.
|
Watering every two hours of active operations or sufficiently often to keep
the area adequately wetted; |
|
|
ii.
|
Applying chemical dust suppressants consistent with manufacturer's directions; |
|
|
iii.
|
Maintaining a gravel cover with a silt content that is less than five (5) percent
and asbestos content that is less than 0.25 percent, as determined using an approved asbestos bulk test method,
to a depth of three (3) inches on the surface being used for travel; or |
|
|
iv.
|
Any other measure as effective as the measures listed above. |
|
|
|
|
(E)
|
Control for earthmoving activities which shall include one or more of the
following:
|
1.
|
Pre-wetting the ground to the depth of anticipated cuts; |
|
2.
|
Suspending grading operations when wind speeds are high enough to result
in dust emissions crossing the property line, despite the application of dust mitigation measures; |
|
3.
|
Application of water prior to any land clearing; or |
|
4.
|
Any other measure as effective as the measures listed above. |
|
|
|
|
(F)
|
Control for Off-Site Transport. The owner / operator shall ensure that no trucks are allowed to transport
excavated material off-site unless:
|
1.
|
Trucks are maintained such that no spillage can occur from holes or other openings
in cargo compartments; and |
|
2.
|
Loads are adequately wetted and either: |
|
|
i.
|
Covered with tarps; or |
|
|
ii.
|
Loaded such that the material does not touch the front, back, or sides
of the cargo compartment at any point less than six inches from the top and that no point of the
load extends above the top of the cargo compartment. |
|
|
|
|
(G)
|
Post Construction Stabilization of Disturbed Areas. Upon completion of the project, disturbed
surfaces shall be stabilized using one or more of the following methods:
|
1.
|
Establishment of a vegetative cover; |
|
2.
|
Placement of at least three (3.0) inches of non-asbestos-containing material; |
|
3.
|
Paving; |
|
4.
|
Any other measure deemed sufficient to prevent wind speeds of ten (10) miles
per hour or greater from causing visible dust emissions. |
|
|
|
|
(H)
|
Air Monitoring for Asbestos (If Required by the APCO).
|
1.
|
If required by the district APCO, the plan must include an air-monitoring component. |
|
2.
|
The air monitoring component shall specify the following: |
|
|
i.
|
Type of air sampling device(s); |
|
|
ii.
|
Siting of air sampling device(s); |
|
|
iii.
|
Sampling duration and frequency; and |
|
|
iv.
|
Analytical method. |
|
|
|
|
(I)
|
Frequency of Reporting: The plan shall state how often the items specified in subsection (e)(5)(B), and
any other items identified in the plan, will be reported to the district. |
|
|
(5)
|
Recordkeeping and Reporting Requirements. |
|
|
|
(A)
|
Recordkeeping Requirements: The
owner / operator shall maintain all of the following records for at least seven (7) years following
the completion of the construction project:
|
1.
|
The results of any air monitoring conducted at the request of the APCO; |
|
2.
|
The documentation for any geologic evaluation conducted on the property
for the purposes of obtaining an exemption, except the archive of collected samples which may be discarded at the
expiration of the exemption or one (1) year after the exemption is granted whichever is less; and |
|
3.
|
The results of any asbestos bulk sampling that meets any of the following
conditions: |
|
|
i.
|
The asbestos bulk sampling was conducted by the owner / operator to
document the applicability of or compliance with this section, or |
|
|
ii.
|
The asbestos bulk sampling was done at the request of the district APCO. |
|
|
|
|
(B)
|
Reporting Requirements:
The owner / operator of any grading or construction operation subject to this section shall submit the following
to the District:
|
1.
|
The results of any air monitoring conducted at the request of the APCO; and |
|
2.
|
The results of any asbestos bulk sampling that meets any of the following conditions: |
|
|
i.
|
Asbestos bulk sampling conducted by the owner / operator to document applicability
of or compliance with this section; or |
|
|
ii.
|
Asbestos bulk sampling done at the request of the APCO. |
|
|
(f)
|
Requirements for Quarrying and Surface Mining Operations. |
|
|
(1)
|
No person shall engage in any quarrying or surface mining operation that
meets the criteria of subsections (b)(1) or (b)(2) unless an Asbestos Dust Mitigation Plan for the operation
has been submitted to and approved by the District and the fugitive dust mitigation measures specified
in the Plan are implemented and maintained throughout the duration of any quarrying or surface mining operation
except, |
|
|
|
(A)
|
Pre-Existing Operations: The owner or operator of any quarrying or surface mining operation that
was in operation before the date this section is implemented as determined pursuant to subsection (a)
that has not obtained district approval of the asbestos dust mitigation plan may continue operating if all the following
conditions are met:
|
1.
|
The owner / operator has submitted an asbestos dust mitigation plan to the
district at least sixty (60) days prior to the date specified in subsection (a); |
|
2.
|
The owner / operator implements all of the dust mitigation measures specified
in subsections (f)(2)(B) and (f)(2)(C) by the effective date specified in subsection (a) and maintains
them until the provisions of an approved asbestos dust mitigation plan are implemented; and |
|
3.
|
The owner / operator implements the provisions of the asbestos dust mitigation
plan within fourteen (14) days following district approval of the plan. |
|
|
|
|
(B)
|
Mineral Exploration Activities: Mineral exploration activities as defined in the California Public Resources
Code section 2714(d) in an area meeting any of the conditions of subsection (b) are not required to submit
an asbestos dust mitigation plan but shall instead implement and maintain the following measures throughout
the duration of the activity:
|
1.
|
Limit vehicle speeds on the site to fifteen (15) miles per hour or less; |
|
2.
|
Apply sufficient water during any ground disturbance to prevent visible
dust from crossing the property line; |
|
3.
|
Keep disturbed areas and storage piles adequately wetted until they are permanently
stabilized; |
|
4.
|
Install a track-out prevention device designed to prevent track-out onto
any paved public road; |
|
5.
|
Clean up any visible track-out at the end of the workday or at a minimum
within twenty-four (24) hours; and |
|
6.
|
Cover, treat with a chemical dust suppressant, or otherwise stabilize any disturbed
areas when operations cease for more than seven (7) days. |
|
|
|
(2)
|
The owner / operator of any quarry or surface mine that meets any of the
criteria in subsection (b)(3) shall: |
|
|
|
(A)
|
Notify the APCO no later than the next business day of the discovery. |
|
|
|
(B)
|
Implement all the following measures within twenty-four (24) hours following
the discovery:
|
1.
|
Keep stock and working piles adequately wetted during the addition and removal
of material; |
|
2.
|
Keep on-site unpaved roads, parking lots, and staging areas stabilized using
one of the following measures: |
|
|
i.
|
Adequately Wetted; or |
|
|
ii.
|
Controlled Using Dust Palliatives or Suppressants; or |
|
|
iii.
|
Paving; or |
|
|
iv.
|
Covered to a depth of three (3) inches with gravel that contains less than
0.25 percent asbestos as determined using an approved asbestos bulk test method; |
|
3.
|
Keep exposed areas and inactive stockpiles that are prone to mechanical
or wind disturbances: |
|
|
i.
|
Adequately Wetted; or |
|
|
ii.
|
Controlled Using Dust Palliatives or Suppressants, Paving, Wind Berms
or Breaks; or |
|
|
iii.
|
Covered with tarps or material that contains less than 0.25 percent asbestos
as determined using an approved asbestos bulk test method; |
|
4.
|
Ensure that materials to be quarried, excavated, or graded are adequately
wetted; |
|
5.
|
Ensure that all loads are adequately wetted before and during truck loading
operations; |
|
6.
|
Ensure that all trucks transporting materials off-site meet the conditions
of either paragraph i or paragraph ii at the time the truck leaves the site: |
|
|
i.
|
Loads are adequately wetted and covered with tarps; or |
|
|
ii.
|
Loads are adequately wetted and the material does not touch the front
back or sides of the cargo compartment at any point less than six (6) inches from
the top and no point of the load extends above the top of the cargo compartment; and |
|
7.
|
Limit vehicle speeds within the quarry or surface mining operation to fifteen (15) miles per
hour or less. |
|
|
|
|
(C)
|
Implement all of the following measures within fourteen (14) days of the
determination that the operation meets any of the criteria in subsection (b)(3).
|
1.
|
Measures to ensure that material being excavated, crushed, screened, loaded,
transferred or conveyed does not result in any dust that is visible crossing the property line. |
|
2.
|
Measures to ensure that no grinding mill, screening operation, or transfer
point on a belt conveyor discharges into the air any visible emissions other than uncombined water vapor,
for a period aggregating more than three minutes in any one hour which are: |
|
|
i.
|
Fifty percent as dark or darker in shade as that designated as number one
on the Ringlemann Chart, as published by the United States Bureau of Mines; or |
|
|
ii.
|
Of such opacity as to obscure an observers view to a degree equal to
or greater than smoke as described in subsection (f)(2)(C)2.i. or ten (10) percent opacity. |
|
3.
|
Measures to ensure that no crusher discharges into the air any visible emissions
other than uncombined water vapor, for a period aggregating more than three minutes in any one hour which
are: |
|
|
i.
|
Seventy-five percent as dark or darker in shade as that designated as
number one on the Ringlemann Chart, as published by the United States Bureau of Mines; or |
|
|
ii.
|
Of such opacity as to obscure an observers view to a degree equal to
or greater than smoke as described in subsection (f)(3)(C)3.i. or fifteen (15) percent
opacity. |
|
4.
|
Measures for material handling sufficient to meet the requirements of subsections (f)(2)(C)1.
through (f)(2)(C)3. Such measures may include the following: |
|
|
i.
|
Installation and operation of spraybars on all conveyors;
and |
|
|
ii.
|
Installation of shrouds at all drop points. |
|
5.
|
Track-out control and prevention measures which shall include: |
|
|
i.
|
Installation of a gravel pad, grizzly, tire washing system, or paving at least
fifty (50) feet of the access road, and |
|
|
ii.
|
Cleaning any visible track-out off the paved public road using wet sweeping
or a HEPA filter equipped vacuum device at the end of each workday. |
|
6.
|
Stabilization of all on-site roads, parking lots, and staging areas open
to the public by one of the following methods: |
|
|
i.
|
Pave with asphalt or concrete, or |
|
|
ii.
|
Treat with a chemical dust suppressant applied according to manufacturers
directions, or |
|
|
iii.
|
Maintain a gravel cover that has a depth of at least three (3) inches and
contains less than 0.25 percent asbestos as determined using an approved asbestos bulk test method. |
|
|
|
|
(D)
|
Submit an Asbestos Dust Mitigation Plan to the District within fourteen
(14) days and maintain the measures specified in subsections (f)(2)(B) and (f)(2)(C) until the asbestos
dust mitigation measures in the district-approved Asbestos Dust Mitigation Plan are implemented. |
|
|
(3)
|
An Asbestos Dust Mitigation Plan required by subsections (f)(1) and (f)(2)(D)
must include sections which address each of the following topics. |
|
|
|
(A)
|
A Fugitive Dust Mitigation Component which shall, at a minimum, include
the measures specified in subsections (f)(2)(B) and (f)(2)(C), unless the APCO determines that it is appropriate
to add, omit, or modify these measures depending on site-specific parameters. The plan shall also
require that:
|
1.
|
Equipment and operations do not emit dust that is visible crossing the property
line; |
|
2.
|
Crushers do not discharge into the air any visible emissions other than uncombined
water vapor, for a period aggregating more than three minutes in any one hour, which is: |
|
|
i.
|
Seventy-five percent as dark or darker in shade as that designated as
number one on the Ringlemann Chart, as published by the United States Bureau of Mines; or |
|
|
ii.
|
Of such opacity as to obscure an observers view to a degree equal to
or greater than smoke as described in subsection (f)(3)(A)2.i. or fifteen (15) percent
opacity; and |
|
3.
|
Grinding mills, screening operations, and transfer points on belt conveyors
do not discharge into the air any visible emissions other than uncombined water vapor, for a period
aggregating more than three minutes in any one hour, which is: |
|
|
i.
|
Fifty percent as dark or darker in shade as that designated as number one
on the Ringlemann Chart, as published by the United States Bureau of
Mines; or |
|
|
ii.
|
Of such opacity as to obscure an observers view to a degree equal to
or greater than smoke as described in subsection (f)(3)(A)3.i. or ten (10) percent
opacity. |
|
|
|
|
(B)
|
Air Monitoring for Asbestos (If Required by the APCO).
|
1.
|
If required by the district APCO, the plan must include an air monitoring
component. |
|
2.
|
The air monitoring component shall specify the following: |
|
|
i.
|
Type of air sampling device(s); |
|
|
ii.
|
Siting of air sampling device(s); |
|
|
iii.
|
Sampling duration and frequency; and |
|
|
iv.
|
Analytical method. |
|
|
|
|
(C)
|
Frequency of Reporting. The plan shall state how often the items specified in subsection (f)(5)(B),
and any other items identified in the plan, will be reported to the district. |
|
|
(4)
|
Upon petition by the owner / operator the APCO may approve the use of requirements
or restrictions established under other regulatory programs to meet the requirements of subsection (f)
under the following conditions: |
|
|
|
(A)
|
The requirements or restrictions are equivalent to or more stringent than the requirements
of subsection (f); and |
|
|
|
(B)
|
The requirements or restrictions are enforceable by the APCO. |
|
|
(5)
|
Recordkeeping and Reporting Requirements: The owner / operator of a surface mining
or quarrying operation subject to this section must comply with the following recordkeeping and reporting
requirements. |
|
|
|
(A)
|
Recordkeeping Requirements: The owner / operator shall maintain all of the following records for at least
seven (7) years:
|
1.
|
The results of any air monitoring conducted at the request of the APCO; |
|
2.
|
The documentation for any geologic evaluation conducted on the property
for the purpose of obtaining an exemption except, the archive of collected rock samples which may be discarded
at the expiration of the exemption or one (1) year after the district granted or denied the exemption, whichever
comes first; and |
|
3.
|
The results of any asbestos bulk sampling that meets any of the following
conditions: |
|
|
i.
|
The asbestos bulk sampling was conducted by the owner / operator to document
the applicability of, or compliance with
this section; or |
|
&n | |