Comment
We have had on order with Freightliner 11 (S2G class 7) propane
chassis, since June of 2013.

we are now advised that these units wont be shipped until September
2014. 
the dead line for the manufactures delay is next month.

Once these show up, it will take the 4-6 weeks per unit to
reconfigure, removing the tank and installing on the new chassis.

Pacific Truck, our fabrication company can only do 2 at a time
which will put us into 2015 before we can come into compliance.

Not sure how to approach CARB on this issue.